With our ability to schedule the subs, we are keeping things moving.... Saturday & Sunday: Craig continued working on boys' bathroom tile and continued through late evenings this week Tuesday: Drywall was textured Wednesday: Garage doors installed & Septic system install began Thursday:  Craig measured all of the windows to order hurricane shutters Friday:  Painter began… Continue reading Owner Builder Schedule