A busy week…

Monday & Tuesday – Insulation finished by Green Star Panels

IMG_5384

Wednesday – Drywall delivered

IMG_5373

Thursday – Bonus room window upstairs reversed to be installed normally (the window had been installed reversed intentionally so that the drywall could be delivered through the window) AND Craig finished the insulation final touches around wiring, windows and doors as well as extra sound proofing between walls

Friday – Insulation inspection to give us the go ahead with drywall

We are so excited and looking forward to drywall.  How fast can we get this house built and move in…..?!?!?! 🙂

 

 

 

 